Refurb: Clarence Road No.2
New design and build contract at another property on Clarence Road, Teddington. Initial measured survey today with some sketch plans for a rear extension, loft conversion and internal remodel. This property is also our fourth job within the Park Road Conservation Area.
April 2019
Refurb: Summer Road
The kitchen is out at Summer Road, KT8 - now just need to re-wire and prep for new kitchen to be fitted!
April 2019
Side Return: Lindum Road
Last few weeks remaining on Lindum Road. Large wrap around extension at ground floor and a first floor outrigger extension providing an additional bedroom.

Just the external landscaping to go!
April 2019
Site Office No.3
New site office location at Clarence Road - right next to some sleek sliding doors.
April 2019
Measured Survey: Plevna Road
Measured survey today at an end of terraced house in Hampton Village Conservation area. Client is after a small rear extension to accommodate a small shower & wc space.
April 2019
Kitchen Design: Clarence Road No.1
The hand made Italian kitchen is almost complete at Clarence Road. As well as a 4m marble top island unit, this kitchen also features a double oven, large fridge freezer, ample storage + a boiling tap!
March 2019
Refurb: Tennyson Avenue
The grass has gone down at Tennyson Avenue today. Just some external lights to wire up to the new face brickwork.
March 2019
Garden Room: Lindum Road
Cedar cladding and bi-fold doors on at Lindum Road. Just final flooring finishes and skirting to finish off this secure bike storage and garden office.
March 2019
Cabinetry: Clarence Road No.1
Sketches for fitted wardrobes and entertainment units starting to take shape at Clarence Road. Photos of the finished article to come soon!
March 2019
Rear Dormer: Cross Street
Steels and new timber floor joists going down on our little loft conversion at Cross Street.
March 2019
Rear Extension: Fifth Cross Road
Doors going on at Fifth Cross Road. This 6m rear projection has been granted under the larger home extension scheme that allows extension of up to 6m from the rear wall of a semi detached house.
February 2019
Rear Dormer: Cross Street
Steels going up the scaffolding on our little loft in Hampton Hill today! Three in total all 152 x 152 x 30 as specified by our in house structural engineer Camilla.
February 2019
Kitchen Design: Clarence Road
Starting to plan the kitchen layout today at Clarence Road. The size of space available means we can have a bold kitchen island as the focal point for the space. Photos of the finished article to come soon!
January 2019
Rear Extension: Fifth Cross Road
Walls and roof are up on our rear extension down the popular Fifth Cross Road, Twickenham. This 6m rear extension will accommodate new kitchen, utility and study spaces.
January 2019
Renovation: Clarence Road No.1
Concrete has been poured at Clarence Road, Teddington in preparation for us to start detail design for the kitchen. We have also decided to strengthen the existing timber floor joists in prep for a new bathroom above!
December 2018
Renovation: Clarence Road No.1
Ground beam and supporting steels being hoisted into place at Clarence Road. As you can see here even the darkness won't stop our boys working.
December 2018
Garden Room: Selkirk Road
Roof structure is starting to take shape on our Garden Room at Selkirk Road, Twickenham. By using large joists we can create a clear span of over 5m wide. This space at the bottom of the garden will accommodate auxiliary living space, garden storage + a disabled access WC.
December 2018
Renovation: Clarence Road No.1
New softwood staircase throughout the house at Clarence Road that is hand built and fitted by our carpenter John. Oak hand rail and balustrades still to come.
November 2018
Refurb: Tennyson Avenue
The new roof structure is going on at Tennyson Avenue in Twickenham. The existing roof was poorly built and this meant the kitchen space was cold in the winter months. A complete new roof + four large skylights will help to improve this pre-existing rear extension.
November 2018
Renovation: Clarence Road No.1
Steels being craned up today onto the roof at Clarence Road, Teddington. 6 spliced steels are going up into the loft to allow us to form 3 rear dormers that comply within the Teddington Park Conservation area.
November 2018
Renovation: Clarence Road No.1
The roof is off and the ground works have started at this large renovation project on Clarence Road, Teddington. This project should take about nine months to complete and provide two additional bedrooms and a large kitchen extension while also refurbishing every room in the house.